Show Case Study As we head into the last 5 weeks of distance learning we would like to encourage all students to respond to the Music and PE activities that are scheduled on the timetable throughout the week. You do not have to respond or complete the activity on that day but within the week is encouraged.
We completely understand that parents have pressures and work commitments. However, if it all possible please ensure you respond in the seesaw activity, This is required once a week only. The response required is brief and often will only take a few minutes. (Check the instructions for that lesson - outlined in the seesaw activity).
Hide Case Study An audit to test the system of controls over the purchase, distribution, and use of radioactive material is being conducted at a company's plants. The process is well documented, and employees in the safety department are very familiar with the department's procedures. Since the purchasing and facilities departments are involved in the process, the auditor is considering reviewing their radioactive material-handling procedures as well. The auditor should:
- Have confidence in the rigorous and detailed safety department procedures,since that department has the main responsibility for radiation safety,and should not use audit time to review other departments.
- Adjust the engagement schedule and budget,if needed,and interview the appropriate individuals in the purchasing and facilities departments to ascertain whether additional controlsexist that complement those identified within the safety department.
- Test the controls identified within the safety department; if results are unfavorable,the auditor should consider whether to involve the other departments.
- Defer questions regarding purchasing,facilities,and other departments until audit projects can be scheduled for those departments.