Financial CMA Exam (page: 50)
Financial Certified Management Accountant
Updated on: 25-Dec-2025

Viewing Page 50 of 270

Details: Ranking Investment Projects 19

Maloney Company uses a 12% hurdle rate for all capital expenditures and has done the following analysis for four projects for the upcoming year


Which project(s) should Maloney undertake during the upcoming year if it has only $6,000,000 of funds available?

  1. Project 3.
  2. Projects 1 and 2.
  3. Project 1.
  4. Project 2.

Answer(s): C

Explanation:

With only $6,000,000 available and each project costing $4,000,000 or more, no more than one project can be undertaken. Project 1 should be chosen because it has a positive NPV and the highest profitability index. The high profitability index means that the company will achieve the highest NPV per dollar of investment with Project 1.The profitability index facilitates comparison of different-sized investments.




Details: Ranking Investment Projects 19

Mercken Industries is contemplating four projects, Project P, Project Q, Project P, and Project S. The capital costs and estimated after-tax net cash flows of each mutually exclusive project are listed below. Mercken's desired after-tax opportunity cost is 12%, and the company has a capital budget for the year of $450,000. Idle funds cannot be reinvested at greater than 12%.


During this year, Mercken will choose

  1. Projects P, 0, and P.
  2. Projects P, Q, R, and S.
  3. Projects Q and R.
  4. Projects P and Q.

Answer(s): C

Explanation:

Only two of the projects can be selected because three would require more than $450,000 of capital. Project S can immediately be dismissed because it has a negative net present value (NPV). Using the NPV and the profitability index methods, the best investments appear to be 0 and P. The internal rate of return (IPP) method indicates that P is preferable to P. However, it assumes reinvestment of funds during Years 4 and 5 at the lRR (18.7%). Given that reinvestment will be at a rate of at most 12%, the IPP decision criterion appears to be unsound in this situation.




Details: Ranking Investment Projects 19

Mercken Industries is contemplating four projects, Project P, Project Q, Project P, and Project S. The capital costs and estimated after-tax net cash flows of each mutually exclusive project are listed below. Mercken's desired after-tax opportunity cost is 12%, and the company has a capital budget for the year of $450,000. Idle funds cannot be reinvested at greater than 12%.


If Mercken is able to accept only one project, the company would choose

  1. Project P.
  2. Project 0 because it has the highest net present value.
  3. Project P because it has the highest internal rate of return.
  4. Project P because it has the shortest payback period.

Answer(s): B

Explanation:

Because unused funds cannot be invested at a rate greater than 12%, the company should select the investment with the highest net present value. Project Q is preferable to P because its return on the incremental $45000 invested ($235,000 cost of Q--$190,000 cost of P) is greater than 12%.




Details: Ranking Investment Projects 19

The method that recognizes the time value of money by discounting the after-tax cash flows over the life of a project, using the company's minimum desired rate of return is the

  1. Accounting rate of return method.
  2. Net present value method.
  3. Internal rate of return method.
  4. Payback method.

Answer(s): B

Explanation:

The net present value (NPV) method computes the discounted present value of future cash inflows to determine whether they are greater than the initial cash outflow. The discount rate (cost of capital or hurdle rate) must be known to discount the future cash inflows. If the NPV is positive (present value of future cash inflows exceeds initial cash outflow), the project should be accepted. If the NPV is negative, the project should be rejected.




Details: Ranking Investment Projects 19

Mulva Inc. is considering the following five independent projects:


The company has a target capital structure which is 40 percent debt and 60 percent equity. The company can issue bonds with a yield to maturity of 10 percent. The company has $900000 in retained earnings, and the current stock price is $40 per share. The flotation costs associated with issuing new equity are $2 per share. Mulva's earnings are expected to continue to grow at 5 percent per year. Next year's dividend (D1) is forecasted to be $2.50. The firm faces a 40 percent tax rate. What is the size of Mulva's capital budget?

  1. $1,200,000
  2. $1,750,000
  3. $2,400,000
  4. $800,000

Answer(s): B

Explanation:

The size of Mulva's capital budget will be determined by the number of projects it can profitably undertake, i.e., those projects for which the IRR is greater than the applicable weighted average cost of capital.
First, the cost of each type of capital must be determined. The formula for calculating the cost of retained earnings is ks = (D1 + Po) + G, where D equals the dividend after year one, P0 equals the current stock price, and G equals the expected growth rate. The cost of retained earnings is 11 .25% [($2.50 ÷ $40) + 0.05]. The formula for calculating the cost of new equity is ke = [(D1 + (Po --floating cost)]+ G. The cost of new equity is 11 .58%{[$2.50 + ($40 --$2)] + 0 .05}.
Given the firm's target capital structure and its retained earnings balance of $900,000, the firm can raise $1 500,000 with debt and retained earnings before it must use outside equity. Therefore, the WACC for $0 -- $1 500,000 of financing is equal to 9.15% [04 (0.10)(1 --04) + 0.6(0.1125) = 0.0915]. Above $1,500,000, the firm must issue some new equity, so the WACC is 9.35% [04(0.10)(1 --04) + 0.6(0.1158) = 0.0935]. Projects A, B, and C will definitely be undertaken because the IRR is greater than the WACC. Next, determine whether Project D will be profitable. Financing Projects A, B, and C, requires $1 200,000 in capital. Therefore, the $550,000 needed for Project D would involve financing $300,000 with debt and retained earnings and $250,000 with debt and equity. Thus, the WACC for Project D is 9.24% [($300,000 + $550,000) x 0.0935], which is less than Project D's IRR. Thus, Projects A, B, C, and D should be accepted, and the firm's capital budget is $1 750,000.



Viewing Page 50 of 270



Share your comments for Financial CMA exam with other users:

Wali 6/4/2023 10:07:00 PM

thank you for making the questions and answers intractive and selectable.
UNITED STATES


Nawaz 7/18/2023 1:10:00 AM

answers are correct?
UNITED STATES


das 6/23/2023 7:57:00 AM

can i belive this dump
INDIA


Sanjay 10/15/2023 1:34:00 PM

great site to practice for sitecore exam
INDIA


jaya 12/17/2023 8:36:00 AM

good for students
UNITED STATES


Bsmaind 8/20/2023 9:23:00 AM

nice practice dumps
Anonymous


kumar 11/15/2023 11:24:00 AM

nokia 4a0-114 dumps
Anonymous


Vetri 10/3/2023 12:59:00 AM

great content and wonderful to have the answers with explanation
UNITED STATES


Ranjith 8/21/2023 3:39:00 PM

for question #118, the answer is option c. the screen shot is showing the drop down, but the answer is marked incorrectly please update . thanks for sharing such nice questions.
Anonymous


Eduardo Ramírez 12/11/2023 9:55:00 PM

the correct answer for the question 29 is d.
Anonymous


Dass 11/2/2023 7:43:00 AM

question no 22: correct answers: bc, 1 per session 1 per page 1 per component always
UNITED STATES


Reddy 12/14/2023 2:42:00 AM

these are pretty useful
Anonymous


Daisy Delgado 1/9/2023 1:05:00 PM

awesome
UNITED STATES


Atif 6/13/2023 4:09:00 AM

yes please upload
UNITED STATES


Xunil 6/12/2023 3:04:00 PM

great job whoever put this together, for the greater good! thanks!
Anonymous


Lakshmi 10/2/2023 5:26:00 AM

just started to view all questions for the exam
NETHERLANDS


rani 1/19/2024 11:52:00 AM

helpful material
Anonymous


Greg 11/16/2023 6:59:00 AM

hope for the best
UNITED STATES


hi 10/5/2023 4:00:00 AM

will post exam has finished
UNITED STATES


Vmotu 8/24/2023 11:14:00 AM

really correct and good analyze!
AZERBAIJAN


hicham 5/30/2023 8:57:00 AM

excellent thanks a lot
FRANCE


Suman C 7/7/2023 8:13:00 AM

will post once pass the cka exam
INDIA


Ram 11/3/2023 5:10:00 AM

good content
Anonymous


Nagendra Pedipina 7/13/2023 2:12:00 AM

q:32 answer has to be option c
INDIA


Tamer Barakat 12/7/2023 5:17:00 PM

nice questions
Anonymous


Daryl 8/1/2022 11:33:00 PM

i really like the support team in this website. they are fast in communication and very helpful.
UNITED KINGDOM


Curtis Nakawaki 6/29/2023 9:13:00 PM

a good contemporary exam review
UNITED STATES


x-men 5/23/2023 1:02:00 AM

q23, its an array, isnt it? starts with [ and end with ]. its an array of objects, not object.
UNITED STATES


abuti 7/21/2023 6:24:00 PM

cool very helpfull
Anonymous


Krishneel 3/17/2023 10:34:00 AM

i just passed. this exam dumps is the same one from prepaway and examcollection. it has all the real test questions.
INDIA


Regor 12/4/2023 2:01:00 PM

is this a valid prince2 practitioner dumps?
UNITED KINGDOM


asl 9/14/2023 3:59:00 PM

all are relatable questions
CANADA


Siyya 1/19/2024 8:30:00 PM

might help me to prepare for the exam
Anonymous


Ted 6/21/2023 11:11:00 PM

just paid and downlaod the 2 exams using the 50% sale discount. so far i was able to download the pdf and the test engine. all looks good.
GERMANY