Financial Certified Management Accountant CMA Dumps in PDF

Free Financial CMA Real Questions (page: 50)


Details: Ranking Investment Projects 19

Maloney Company uses a 12% hurdle rate for all capital expenditures and has done the following analysis for four projects for the upcoming year


Which project(s) should Maloney undertake during the upcoming year if it has only $6,000,000 of funds available?

  1. Project 3.
  2. Projects 1 and 2.
  3. Project 1.
  4. Project 2.

Answer(s): C

Explanation:

With only $6,000,000 available and each project costing $4,000,000 or more, no more than one project can be undertaken. Project 1 should be chosen because it has a positive NPV and the highest profitability index. The high profitability index means that the company will achieve the highest NPV per dollar of investment with Project 1.The profitability index facilitates comparison of different-sized investments.




Details: Ranking Investment Projects 19

Mercken Industries is contemplating four projects, Project P, Project Q, Project P, and Project S. The capital costs and estimated after-tax net cash flows of each mutually exclusive project are listed below. Mercken's desired after-tax opportunity cost is 12%, and the company has a capital budget for the year of $450,000. Idle funds cannot be reinvested at greater than 12%.


During this year, Mercken will choose

  1. Projects P, 0, and P.
  2. Projects P, Q, R, and S.
  3. Projects Q and R.
  4. Projects P and Q.

Answer(s): C

Explanation:

Only two of the projects can be selected because three would require more than $450,000 of capital. Project S can immediately be dismissed because it has a negative net present value (NPV). Using the NPV and the profitability index methods, the best investments appear to be 0 and P. The internal rate of return (IPP) method indicates that P is preferable to P. However, it assumes reinvestment of funds during Years 4 and 5 at the lRR (18.7%). Given that reinvestment will be at a rate of at most 12%, the IPP decision criterion appears to be unsound in this situation.




Details: Ranking Investment Projects 19

Mercken Industries is contemplating four projects, Project P, Project Q, Project P, and Project S. The capital costs and estimated after-tax net cash flows of each mutually exclusive project are listed below. Mercken's desired after-tax opportunity cost is 12%, and the company has a capital budget for the year of $450,000. Idle funds cannot be reinvested at greater than 12%.


If Mercken is able to accept only one project, the company would choose

  1. Project P.
  2. Project 0 because it has the highest net present value.
  3. Project P because it has the highest internal rate of return.
  4. Project P because it has the shortest payback period.

Answer(s): B

Explanation:

Because unused funds cannot be invested at a rate greater than 12%, the company should select the investment with the highest net present value. Project Q is preferable to P because its return on the incremental $45000 invested ($235,000 cost of Q--$190,000 cost of P) is greater than 12%.




Details: Ranking Investment Projects 19

The method that recognizes the time value of money by discounting the after-tax cash flows over the life of a project, using the company's minimum desired rate of return is the

  1. Accounting rate of return method.
  2. Net present value method.
  3. Internal rate of return method.
  4. Payback method.

Answer(s): B

Explanation:

The net present value (NPV) method computes the discounted present value of future cash inflows to determine whether they are greater than the initial cash outflow. The discount rate (cost of capital or hurdle rate) must be known to discount the future cash inflows. If the NPV is positive (present value of future cash inflows exceeds initial cash outflow), the project should be accepted. If the NPV is negative, the project should be rejected.




Details: Ranking Investment Projects 19

Mulva Inc. is considering the following five independent projects:


The company has a target capital structure which is 40 percent debt and 60 percent equity. The company can issue bonds with a yield to maturity of 10 percent. The company has $900000 in retained earnings, and the current stock price is $40 per share. The flotation costs associated with issuing new equity are $2 per share. Mulva's earnings are expected to continue to grow at 5 percent per year. Next year's dividend (D1) is forecasted to be $2.50. The firm faces a 40 percent tax rate. What is the size of Mulva's capital budget?

  1. $1,200,000
  2. $1,750,000
  3. $2,400,000
  4. $800,000

Answer(s): B

Explanation:

The size of Mulva's capital budget will be determined by the number of projects it can profitably undertake, i.e., those projects for which the IRR is greater than the applicable weighted average cost of capital.
First, the cost of each type of capital must be determined. The formula for calculating the cost of retained earnings is ks = (D1 + Po) + G, where D equals the dividend after year one, P0 equals the current stock price, and G equals the expected growth rate. The cost of retained earnings is 11 .25% [($2.50 ÷ $40) + 0.05]. The formula for calculating the cost of new equity is ke = [(D1 + (Po --floating cost)]+ G. The cost of new equity is 11 .58%{[$2.50 + ($40 --$2)] + 0 .05}.
Given the firm's target capital structure and its retained earnings balance of $900,000, the firm can raise $1 500,000 with debt and retained earnings before it must use outside equity. Therefore, the WACC for $0 -- $1 500,000 of financing is equal to 9.15% [04 (0.10)(1 --04) + 0.6(0.1125) = 0.0915]. Above $1,500,000, the firm must issue some new equity, so the WACC is 9.35% [04(0.10)(1 --04) + 0.6(0.1158) = 0.0935]. Projects A, B, and C will definitely be undertaken because the IRR is greater than the WACC. Next, determine whether Project D will be profitable. Financing Projects A, B, and C, requires $1 200,000 in capital. Therefore, the $550,000 needed for Project D would involve financing $300,000 with debt and retained earnings and $250,000 with debt and equity. Thus, the WACC for Project D is 9.24% [($300,000 + $550,000) x 0.0935], which is less than Project D's IRR. Thus, Projects A, B, C, and D should be accepted, and the firm's capital budget is $1 750,000.



Share your comments for Financial CMA exam with other users:

A
ash
7/11/2023 3:00:00 AM

please upload dump, i have exam in 2 days

S
Sneha
8/17/2023 6:29:00 PM

this is useful

S
sachin
12/27/2023 2:45:00 PM

question 232 answer should be perimeter not netowrk layer. wrong answer selected

T
tomAws
7/18/2023 5:05:00 AM

nice questions

R
Rahul
6/11/2023 2:07:00 AM

hi team, could you please provide this dump ?

T
TeamOraTech
12/5/2023 9:49:00 AM

very helpful to clear the exam and understand the concept.

C
Curtis
7/12/2023 8:20:00 PM

i think it is great that you are helping people when they need it. thanks.

S
sam
7/17/2023 6:22:00 PM

cannot evaluate yet

N
nutz
7/20/2023 1:54:00 AM

a laptops wireless antenna is most likely located in the bezel of the lid

R
rajesh soni
1/17/2024 6:53:00 AM

good examplae to learn basic

T
Tanya
10/25/2023 7:07:00 AM

this is useful information

N
Nasir Mahmood
12/11/2023 7:32:00 AM

looks usefull

J
Jason
9/30/2023 1:07:00 PM

question 81 should be c.

T
TestPD1
8/10/2023 12:22:00 PM

question 18 : response isnt a ?

A
ally
8/19/2023 5:31:00 PM

plaese add questions

D
DIA
10/7/2023 5:59:00 AM

is dumps still valid ?

A
Annie
7/7/2023 8:33:00 AM

thanks for this

A
arnie
9/17/2023 6:38:00 AM

please upload questions

T
Tanuj Rana
7/22/2023 2:33:00 AM

please upload the question dump for professional machinelearning

F
Future practitioner
8/10/2023 1:26:00 PM

question 4 answer is c. this site shows the correct answer as b. "adopt a consumption model" is clearly a cost optimization design principle. looks like im done using this site to study!!!

A
Ace
8/3/2023 10:37:00 AM

number 52 answer is d

N
Nathan
12/17/2023 12:04:00 PM

just started preparing for my exam , and this site is so much help

C
Corey
12/29/2023 5:06:00 PM

question 35 is incorrect, the correct answer is c, it even states so: explanation: when a vm is infected with ransomware, you should not restore the vm to the infected vm. this is because the ransomware will still be present on the vm, and it will encrypt the files again. you should also not restore the vm to any vm within the companys subscription. this is because the ransomware could spread to other vms in the subscription. the best way to restore a vm that is infected with ransomware is to restore it to a new azure vm. this will ensure that the ransomware is not present on the new vm.

R
Rajender
10/18/2023 3:54:00 AM

i would like to take psm1 exam.

B
Blessious Phiri
8/14/2023 9:53:00 AM

cbd and pdb are key to the database

A
Alkaed
10/19/2022 10:41:00 AM

the purchase and download process is very much streamlined. the xengine application is very nice and user-friendly but there is always room for improvement.

D
Dave Gregen
9/4/2023 3:17:00 PM

please upload p_sapea_2023

S
Sarah
6/13/2023 1:42:00 PM

anyone use this? the question dont seem to follow other formats and terminology i have been studying im getting worried

S
Shuv
10/3/2023 8:19:00 AM

good questions

R
Reb974
8/5/2023 1:44:00 AM

hello are these questions valid for ms-102

M
Mchal
7/20/2023 3:38:00 AM

some questions are wrongly answered but its good nonetheless

S
Sonbir
8/8/2023 1:04:00 PM

how to get system serial number using intune

M
Manju
10/19/2023 1:19:00 PM

is it really helpful to pass the exam

L
LeAnne Hair
8/24/2023 12:47:00 PM

#229 in incorrect - all the customers require an annual review

AI Tutor 👋 I’m here to help!