Financial Certified Management Accountant CMA Dumps in PDF

Free Financial CMA Real Questions (page: 45)


Details: Risk Analysis and Real Options 20

The internal rate of return for a project can be determined

  1. If the internal rate of return is greater than the firm's cost of capital.
  2. Only if the project cash flows are constant.
  3. By finding the discount rate that yields a net present value of zero for the project.
  4. By subtracting the firm's cost of capital from the project's profitability index.

Answer(s): C

Explanation:

The IRR is a capital budgeting technique that calculates the interest rate that yields a net present value equal to $0. It is the interest rate that will discount the future cash flows to an amount equal to the initial cost of the project. Thus, the higher the PR, the more favorable the ranking of the project.




Details: Risk Analysis and Real Options 20

Carco, Inc. wants to use discounted cash flow techniques when analyzing its capital investment projects. The company is aware of the uncertainly involved in estimating future cash flows. A simple method some companies employ to adjust for the uncertainly inherent in their estimates is to

  1. Prepare a direct analysis of the probability of outcomes.
  2. Use accelerated depreciation.
  3. Adjust the minimum desired rate of return.
  4. Increase the estimates of the cash flows.

Answer(s): C

Explanation:

Uncertainly can be compensated for by adjusting the desired rate of return. If projects have relatively uncertain returns, a higher rate should be required. A lower rate of return may be acceptable given greater certainly. The concept is that with increased risk should come increased rewards1 i.e., a higher rate of return.




Details: Risk Analysis and Real Options 20

The accountant of Ronier, Inc. has prepared an analysis of a proposed capital project using discounted cash flow techniques. One manager has questioned the accuracy of the results because the discount factors employed in the analysis have assumed the cash flows occurred at the end of the year when the cash flows actually occurred uniformly throughout each year. The net present value calculated by the accountant will

  1. Not be in error.
  2. Be slightly overstated.
  3. Be unusable for actual decision making.
  4. Be slightly understated but usable.

Answer(s): D

Explanation:

The effect of assuming cash flows occur at the end of the year simply understates the present values of the future cash flows, in reality, they probably occur on the average at mid-year.




Details: Risk Analysis and Real Options 20

High-Tech Industries is considering the acquisition of a new state-of-the-art manufacturing machine to replace a less efficient machine. Hi-Tech has completed a net present value analysis and found it to be favorable. Which one of the following factors should not be of concern to Hi-Tech in its acquisition considerations?

  1. The availability of any necessary financing.
  2. The probability of near-term technological changes to the manufacturing process.
  3. The investment tax credit.
  4. Maintenance requirements, warranties, and availability of service arrangements.

Answer(s): C

Explanation:

The investment tax credit is of no concern because it no longer exists. The 1986 Tax Reform Act eliminated the investment tax credit.




Details: Risk Analysis and Real Options 20

The internal rate of return on an investment

  1. Usually coincides with the company's hurdle rate.
  2. Disregards discounted cash flows.
  3. May produce different rankings from the net present value method on mutually exclusive projects.
  4. Would tend to be reduced if a company used an accelerated method of depreciation for tax purposes rather than the straight-line method.

Answer(s): C

Explanation:

Investment projects may be mutually exclusive under conditions of capital rationing (limited capital). In other words, scarcity of resources will prevent an entity from undertaking all available profitable activities. Under the PR method, an interest rate is computed such that the present value of the expected future cash flows equals the cost of the investment (NPV = 0). The IRR method assumes that the cash flows will be reinvested at the IRR. The NPV is the excess of the present value of the estimated net cash inflows over the net cost of the investment. The cost of capital must be specified in the NPV method. An assumption of the NPV method is that cash flows from the investment will be reinvested at the particular project's cost of capital. Because of the difference in the assumptions regarding the reinvestment of cash flows, the two methods will occasionally give different answers regarding the ranking of mutually exclusive projects. Moreover, the IRR method may rank several small, short-lived projects ahead of a large project with a lower rate of return but with a longer life span. However, the large project might return more dollars to the company because of the larger amount invested and the longer time span over which earnings will accrue. When faced with capital rationing, an investor will want to invest in projects that generate the most dollars in relation to the limited resources available and the size and returns from the possible investments. Thus, the NPV method should be used because it determines the aggregate present value for each feasible combination of projects.



Share your comments for Financial CMA exam with other users:

B
Blessious Phiri
8/15/2023 4:08:00 PM

its giving best technical knowledge

T
Testbear
6/13/2023 11:15:00 AM

please upload

S
shime
10/24/2023 4:23:00 AM

great question with explanation thanks!!

T
Thembelani
5/30/2023 2:40:00 AM

does this exam have lab sections?

S
Shin
9/8/2023 5:31:00 AM

please upload

P
priti kagwade
7/22/2023 5:17:00 AM

please upload the braindump for .net

R
Robe
9/27/2023 8:15:00 PM

i need this exam 1z0-1107-2. please.

C
Chiranthaka
9/20/2023 11:22:00 AM

very useful!

N
Not Miguel
11/26/2023 9:43:00 PM

for this question - "which three type of basic patient or member information is displayed on the patient info component? (choose three.)", list of conditions is not displayed (it is displayed in patient card, not patient info). so should be thumbnail of chatter photo

A
Andrus
12/17/2023 12:09:00 PM

q52 should be d. vm storage controller bandwidth represents the amount of data (in terms of bandwidth) that a vms storage controller is using to read and write data to the storage fabric.

R
Raj
5/25/2023 8:43:00 AM

nice questions

M
max
12/22/2023 3:45:00 PM

very useful

M
Muhammad Rawish Siddiqui
12/8/2023 6:12:00 PM

question # 208: failure logs is not an example of operational metadata.

S
Sachin Bedi
1/5/2024 4:47:00 AM

good questions

K
Kenneth
12/8/2023 7:34:00 AM

thank you for the test materials!

H
Harjinder Singh
8/9/2023 4:16:00 AM

its very helpful

S
SD
7/13/2023 12:56:00 AM

good questions

K
kanjoe
7/2/2023 11:40:00 AM

good questons

M
Mahmoud
7/6/2023 4:24:00 AM

i need the dumb of the hcip security v4.0 exam

W
Wei
8/3/2023 4:18:00 AM

upload the dump please

S
Stephen
10/3/2023 6:24:00 PM

yes, iam looking this

S
Stephen
8/4/2023 9:08:00 PM

please upload cima e2 managing performance dumps

H
hp
6/16/2023 12:44:00 AM

wonderful questions

P
Priyo
11/14/2023 2:23:00 AM

i used this site since 2000, still great to support my career

J
Jude
8/29/2023 1:56:00 PM

why is the answer to "which of the following is required by scrum?" all of the following stated below since most of them are not mandatory? sprint retrospective. members must be stand up at the daily scrum. sprint burndown chart. release planning.

M
Marc blue
9/15/2023 4:11:00 AM

great job. hope this helps out.

A
Anne
9/13/2023 2:33:00 AM

upload please. many thanks!

P
pepe el toro
9/12/2023 7:55:00 PM

this is so interesting

A
Antony
11/28/2023 12:13:00 AM

great material thanks

T
Thembelani
5/30/2023 2:22:00 AM

anyone who wrote this exam recently

P
P
9/16/2023 1:27:00 AM

ok they re good

J
Jorn
7/13/2023 5:05:00 AM

relevant questions

A
AM
6/20/2023 7:54:00 PM

please post

N
Nagendra Pedipina
7/13/2023 2:22:00 AM

q:42 there has to be a image in the question to choose what does it mean from the options

AI Tutor 👋 I’m here to help!