An organization receives the most value from an internal audit activity's enterprise-wide risk assessment when the auditor

  1. Focuses primarily on enterprise-level risks
  2. Considers activities at all levels of the organization
  3. Reviews special projects and new initiatives
  4. Validates supporting financial and operational data

Answer(s): B



Internal auditors who are concerned with potential risks due to the mishandling of records or transactions should take into consideration

  1. The type and nature of the activities to be examined
  2. Whether employees in key positions of trust are bonded
  3. The history of losses suffered by the company
  4. The results of prior risk assessments

Answer(s): A



A chief audit executive (CAE) used an electronic spreadsheet to facilitate the risk assessment process for a number of different divisions. The spreadsheet included the following factors Complexity of operations Competence of divisional personnel Dollar amount of accounts where management's judgment can affect the expense. The CAE used a group meeting of audit managers to reach a consensus on the competence of divisional personnel. Other factors were assessed as high, medium, or low risk by either the CAE or an audit manager who had audited the division. The CAE weighted each factor and computed a composite risk score. Which of the following statements is correct regarding this risk assessment process?

  1. The risk analysis would not be appropriate because it mixes both quantitative and qualitative factors.
  2. Assessing factors at discrete levels, such as high, medium, and low, is inappropriate for the risk assessment process because the ratings are not quantifiable.
  3. The weighting is subjective and should have been determined through a process such as multiple regression analysis.
  4. Using a subjective group consensus to assess personnel competence is appropriae.

Answer(s): D



Which of the following is a risk factor that a chief audit executive should consider when prioritizing audit work schedules?

I). Quality of internal control
II). Management competence
III). Time of last audit engagement
IV). Degree of change or organizational stability

  1. I and III only
  2. I, II, and IV only
  3. II, III, and IV only
  4. I, II, III, and IV

Answer(s): D



A company has entered into a $20, 000, 000 fixed-price contract with a general contractor for the construction of a new retail outlet. For this contract, which of the following would represent the greatest risk?

  1. Excessive labor charged to the project
  2. Poor physical protection of materials and equipment
  3. Failure to complete the project within budget
  4. Substitution of inferior materials

Answer(s): D



Share your comments for Financial CIA-I exam with other users:

L
Lavanya
11/2/2023 1:53:00 AM

useful information

M
Moussa
12/12/2023 5:52:00 AM

intéressant

M
Madan
6/22/2023 9:22:00 AM

thank you for making the interactive questions

V
Vavz
11/2/2023 6:51:00 AM

questions are accurate

S
Su
11/23/2023 4:34:00 AM

i need questions/dumps for this exam.

L
LuvSN
7/16/2023 11:19:00 AM

i need this exam, when will it be uploaded

M
Mihai
7/19/2023 12:03:00 PM

i need the dumps !

W
Wafa
11/13/2023 3:06:00 AM

very helpful

A
Alokit
7/3/2023 2:13:00 PM

good source

S
Show-Stopper
7/27/2022 11:19:00 PM

my 3rd test and passed on first try. hats off to this brain dumps site.

M
Michelle
6/23/2023 4:06:00 AM

please upload it

L
Lele
11/20/2023 11:55:00 AM

does anybody know if are these real exam questions?

G
Girish Jain
10/9/2023 12:01:00 PM

are these questions similar to actual questions in the exam? because they seem to be too easy

P
Phil
12/8/2022 11:16:00 PM

i have a lot of experience but what comes in the exam is totally different from the practical day to day tasks. so i thought i would rather rely on these brain dumps rather failing the exam.

B
BV
6/8/2023 4:35:00 AM

good questions

K
krishna
12/19/2023 2:05:00 AM

valied exam dumps. they were very helpful and i got a pretty good score. i am very grateful for this service and exam questions

P
Pie
9/3/2023 4:56:00 AM

will it help?

L
Lucio
10/6/2023 1:45:00 PM

very useful to verify knowledge before exam

A
Ajay
5/17/2023 4:54:00 AM

good stuffs

T
TestPD1
8/10/2023 12:19:00 PM

question 17 : responses arent b and c ?

N
Nhlanhla
12/13/2023 5:26:00 AM

just passed the exam on my first try using these dumps.

R
Rizwan
1/6/2024 2:18:00 AM

very helpful

Y
Yady
5/24/2023 10:40:00 PM

these questions look good.

K
Kettie
10/12/2023 1:18:00 AM

this is very helpful content

S
SB
7/21/2023 3:18:00 AM

please provide the dumps

D
David
8/2/2023 8:20:00 AM

it is amazing

U
User
8/3/2023 3:32:00 AM

quesion 178 about "a banking system that predicts whether a loan will be repaid is an example of the" the answer is classification. not regresion, you should fix it.

Q
quen
7/26/2023 10:39:00 AM

please upload apache spark dumps

E
Erineo
11/2/2023 5:34:00 PM

q14 is b&c to reduce you will switch off mail for every single alert and you will switch on daily digest to get a mail once per day, you might even skip the empty digest mail but i see this as a part of the daily digest adjustment

P
Paul
10/21/2023 8:25:00 AM

i think it is good question

U
Unknown
8/15/2023 5:09:00 AM

good for students who wish to give certification.

C
Ch
11/20/2023 10:56:00 PM

is there a google drive link to the images? the links in questions are not working.

J
Joey
5/16/2023 5:25:00 AM

very promising, looks great, so much wow!

A
alaska
10/24/2023 5:48:00 AM

i scored 87% on the az-204 exam. thanks! i always trust

AI Tutor 👋 I’m here to help!