Southwark is negotiating a contract with Orchard to provide software and IT services. Orchard will manufacture and install the products which are contractually supplied by IBM. Southwark's procurement manager is worried that during the contract there would be some problems that they would not able to claim for damages from Orchard. Which of the following should be included in the head contract so that Southward can sue IBM, should the need arise?
Answer(s): C
A Collateral Warranty is a contract under which a consultant, a building contractor or a sub- contractor warrants to a third party that is has fulfilled its obligations under its professional appointment, building contract or sub-contract. The purpose of a Collateral Warranty is to give a third party, who is not a party to the original contract, rights to enforce that original contract. In this case, IBM is the subcontractor, then purchaser can use collateral warranty deed to bind them.
- Collateral Warranties an Overview- CIPS study guide page 39-40 LO 1, AC 1.2
In a contract, both buyer and supplier agreed the lead time is 3 days. The contract also requires that any variation must be made in writing. Then the buyer places an order by phone call and requests delivery the next day, but the supplier delivers on the third day since the order. Can buyer refuse to pay as supplier did not deliver per time?
Answer(s): A
Lead time is the amount of time that passes from the start of a process until its conclusion. In procurement, lead time can be understood as the amount of time that passes from placing an order until the delivery.In the scenario, the contract requires the supplier to make a delivery within 3 days since the order. This contract can only be amended with written consent from both parties. Therefore, there is no ground for shortening the lead time to 1 day because the new lead time is only the request of buyer. Then the supplier still makes delivery within agreed lead time. LO 1, AC 1.1
Which of the following are reasons why a purchaser wants to embed a subcontracting clause into the main contract? Select TWO that apply:
Answer(s): D
There are number of reasons why the purchaser will want to control the supplier's subcontracting:- Supply chain transparency: Normally the purchaser has invested a lot of effort into selecting the right contractor. However, the main contractor's selection of subcontractor might not be in such careful manner, which may result in poor performance. Purchaser must know who subcontractors are. Controlling the subcontracting process can help the purchaser control the outcome.- Contract terms: the purchaser's requirements must be reflected in the subcontracts. The subcontracting clauses may require the main contractor to do this.- Liability: the main contractor may subcontract the whole or a part of its liabilities. Subcontracting clause may bind the contractor to be liable with the work, it cannot just blame the subcontractor for any faults.
CIPS study guide page 154-155 LO 3, AC 3.2
In a sale contract, a clause requires the seller to "defend, reimburse, and hold harmless" the buyer and its personnel from and against any and all damages arising in connection with some specific circumstances. This clause is an example of...?
An indemnity is a promise by one party to compensate another for the loss suffered as a consequence of a specific event, called the ''trigger event''. The trigger event can be anything defined by the parties, including:- A breach of contract;- A party's fault or negligence;- A specific action.An indemnity operates as a transfer of risks between the parties, and changes what they would otherwise be liable for or entitled to under a normal damage claim. Force Majeure Provisions: A force majeure event refers to the occurrence of an event which is outside the reasonable control of a party and which prevents that party from performing its obligations under a contract.Liquidated damages are presented in certain legal contracts as an estimate of otherwise intangible or hard-to-define losses to one of the parties. It is a provision that allows for the payment of a specified sum should one of the parties be in breach of contract. LO 3, AC 3.2
Which of the following encourages social and environmental criteria in public sector contracting in the UK?
Answer(s): B
Social and environmental criteria are increasingly encouraged in public sector contracting. In the UK, The Public Services (Social Value) Act 2012 encourages public organising to apply social and environmental criteria in contract.
CIPS study guide page 98-99 LO 2, AC 2.1
Share your comments for CIPS L4M3 exam with other users:
please upload the c_activate22 dump questions with answer
q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president
this was on the exam as of 1211/2023
great for prep
i think in question 7 the first answer should be power bi portal (not power bi)
on question 10 and so far 2 wrong answers as evident in the included reference link.
wonderful material
i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!
correct answer for question 92 is c -aws shield
great !! it is really good
explanations for the answers are to the point.
how can rea next
question: 128 d is the wrong answer...should be c
thanks for az 700 dumps
thank you for this tableau dumps . it will helpfull for tableau certification
good content
just testing if the comments are real
very helpful for exam preparation
question 11: https://help.salesforce.com/s/articleview?id=sf.admin_lead_to_patient_setup_overview.htm&type=5
i think the answer to question 42 is b not c
thanks for the dump
fantastic assessments
i find the xengine test engine simulator to be more fun than reading from pdf.
nice document
thank you for making the questions and answers intractive and selectable.
answers are correct?
can i belive this dump
great site to practice for sitecore exam
good for students
nice practice dumps
nokia 4a0-114 dumps
great content and wonderful to have the answers with explanation
for question #118, the answer is option c. the screen shot is showing the drop down, but the answer is marked incorrectly please update . thanks for sharing such nice questions.
the correct answer for the question 29 is d.